Re: KEY DATE in Inspection Lot

$
0
0

I'm not sure myself as I don't work with material versions.  But it sounds like something related to that.  The thing to understand is that the inspc lot start date can be influenced by several differnt type s of documents.  So 04 lots can get their start date from the planed start date of the order, (I.e. When early lot creation is used).  Its not necessarily always that the lot creation date = the lot start date.

 

hopefully maybe some folks more familiar with material versions might be able to shed more light on this.

 

Craig