Re: Issue with Basic Start Date and Scheduled Start Date on Production Orders

$
0
0

Hi Eswar,

 

 

Please maintain minimum overlap time and Min Send ahead quantity for operations
which are going to overlap. You can check this in routing under operation
detail tab.

 

 

If you have tick other than "No
Overlapping" than you have to maintain the time and quantity data.

 

Overlapping.JPG

Also it should be maintain such that the Overlap time should he more than
the minimum send-ahead quantity processing time this is very important.

 

 

That means if for processing min send ahead quantity 10 min are required than min
overlap time should be greater than 10 min.

 

 

Regards,

 

 

Amarnath Dube